15 Swift Terrace

Project Blog

Proposed Renderings 

Rendering Of Living Space
Rendering Of Living Space

press to zoom
Rendering Of Finished Bath
Rendering Of Finished Bath

press to zoom
Swift Exterior Rendering
Swift Exterior Rendering

press to zoom
Rendering Of Living Space
Rendering Of Living Space

press to zoom
1/3

7/16/2018

Unit 3 is on the market!

Exterior 1
Exterior 1

press to zoom
Exterior 2
Exterior 2

press to zoom
Parking Area
Parking Area

press to zoom
Exterior 1
Exterior 1

press to zoom
1/16

5/31/2018

These two remaining units are going to hit the market in June. The painters are in touching up the units and granite is about to arrive. The floors will be polyurethaned at the very end of the project and the driveway should be paved in the next 10 days. 

Swift Exterior
Swift Exterior

press to zoom
Swift Exterior
Swift Exterior

press to zoom
Harrison showing the property
Harrison showing the property

press to zoom
Swift Exterior
Swift Exterior

press to zoom
1/5

5/4/2018

Our project is almost complete. We've currently pre-sold one of the three units and are working hard to lock up the other two. Hardwood floors are being wrapped up, doors and trim are mostly in, and we're working on our finish utilities next week. We're still on track to wrap up around the end of May.   

White Oak Hardwood Flooring
White Oak Hardwood Flooring

press to zoom
Contemporary Bath
Contemporary Bath

press to zoom
First Unit Accent Tile
First Unit Accent Tile

press to zoom
White Oak Hardwood Flooring
White Oak Hardwood Flooring

press to zoom
1/9

4/4/2018

We unfortunately had some back end issues that prevented us from being able to update our website on a bi-weekly basis. With that said, our project has made tremendous strides. From these photos, you can see our sheet-rock, rough plumbing and electric is done. The sprinkler system is installed and we're priming for paint. 

Exterior
Exterior

press to zoom
Open Concept Floor Plan
Open Concept Floor Plan

press to zoom
Sub Panels In Each Unit
Sub Panels In Each Unit

press to zoom
Exterior
Exterior

press to zoom
1/10

10/12/2017

The original building has been demolished, and all site work should be completed on the build by the end of this week. Our foundation has been poured and you can now see the footprint of the building. Refer to the rendering below to see how unit 2 and 3 will cantilever over foundation providing covered parking. 

Driveway area to covered parking
Driveway area to covered parking

press to zoom
Swift Foundation Work
Swift Foundation Work

press to zoom
Swift Foundation Work 2
Swift Foundation Work 2

press to zoom
Driveway area to covered parking
Driveway area to covered parking

press to zoom
1/3

10/9/2017

We closed on this lot June 21st, 2017. This will be our first new construction project which consists of the demolition of a single family property and the construction of a three unit condominium building with off street parking. The lot size was large enough that we could get these plans approved without any zoning relief.  

Swift Initial Rendering
Swift Initial Rendering

press to zoom
Swift Initial Rendering
Swift Initial Rendering

press to zoom
1/1